Midland Bay Landing Project

Midland Bay Landing will transform 40 acres of former industrial waterfront into a vibrant, mixed-use, pedestrian-oriented neighbourhood that enhances Midland’s downtown and harbour.

Midland Bay Landing

The timeline follows the phases that will take place in 2025.

1

The Vision

February to April 2025 - Phase 1: Consultants, Town Council, staff and the public collaborated on the Midland Bay Landing vision.

2

Engagement Survey

March 20, 2025 - Survey open for two weeks.

3

MBL Open House Event

April 15, 2025 - Public information sessions (afternoon and evening) about Midland Bay Landing.

4

Market the Opportunity

May to September 2025 - Phase 2: Consultants and staff used the framework created from public collaboration to develop and issue the Request for Expressions of Interest.

5

Consultant Presentation

May 21,2025 - Consultants presented a "What We Heard" presentation to Council.

6

Request for Expressions of Interest (RFEI)

June 18, 2025 to 2pm August 8, 2025 - Submissions in response to the RFEI were being accepted.

7

Selecting the Developer

September to December 2025 - Phase 3: Town Council will select the right developer with a shared vision following review and evaluation of proposals.