Ellen Street Reconstruction

Project Status: Completed on Friday, November 28, 2025


Ellen Street underwent reconstruction from King Street to Johnson Street. The project started in June 2025. Emergency access was maintained at all times. 

This project included: 

  • Replacement of existing sanitary sewer and watermain, including services to property line.
  • Drainage improvements and storm sewer upgrades.
  • Full road reconstruction, including new curb, sidewalks, granulars and asphalt.
  • Reinstatement of all disturbed areas to previous or better condition, including sections of driveways or boulevard affected by construction.

Project Area

  • Ellen Street Reconstruction Map

Ellen Street Reconstruction Notices

A paper notice was delivered to properties within the affected area on Ellen Street. The notice outlines information for property owners and potential affected services. View full notice.

Questions about Construction?

If you have any questions or comments about the Ellen Street Reconstruction project contact Chip or Steve using the contact information below. Damages should be reported as soon as possible. 

King Infrastructure Inc.

Chip Apetri

Site Superintendent

14 Cedar Pointe Drive, Unit 1510

Barrie, Ontario, L4N 5R7

 

EXP Services Inc.

Steve Pauls, P. Eng.

Project Engineer

14 Cedar Pointe Drive, Unit 1510

Barrie, Ontario, L4N 5R7

 

 

Town of Midland

Bailee Yasher

Senior Project Manager

575 Dominion Ave

Midland, Ontario, L4R 1R2