Posted August 26, 2026: Paving of both sections of Hugel is complete. Completion of pavement markings is expected to be completed this evening and driveway restorations are to begin next week. Simpresca Road has been graded and paving is scheduled to take place next week.
Posted July 30, 2026: The contractor will start working on Hugel Avenue (Woodland–Eighth and George–William) on July 31, cutting the sections of curb they will be replacing to get them ready for removal and replacement the week of August 3. The removal of asphalt, placement of new granular, and placement of new asphalt will follow the curb work and is anticipated to take roughly three weeks to complete. All work on Hugel is scheduled to wrap up by August 21.