Posted October 27, 2026:
The full closure of the Hugel/Eighth intersection that was scheduled for October 28 and 29 has been re-scheduled. The intersection closure is now scheduled to be in place from 7am October 29 to 10pm October 30.
Posted October 26, 2026:
The Town of Midland and CM Drain will be conducting work on Eighth Street that will require a full closure of the Hugel/Eighth intersection, scheduled from 7am October 28 to 10pm October 29. No through-traffic will be permitted, and detour signage will be in place.
Final driveway and asphalt works along Eighth Street is happening from October 26 to October 30. Driveway access restrictions are scheduled to be in place, and street parking will not be permitted during working hours. Oct 23rd notices containing full information have been hand-delivered to impacted properties.
Posted October 16, 2026:
The intersection of Hugel/Eighth has now reopened for traffic.
Posted October 14, 2026:
Watermain work will cause a temporary disruption to water service for some residents on October 15 (inclement weather date: October 16), and driveway access restrictions are scheduled to be in place on October 16 and 19. Notices containing full information have been hand-delivered to impacted properties.
The full road closure of Hugel/Eighth intersection has been extended until further notice, and could be in effect until Friday, October 16. The road remains open to local traffic only, however no through-traffic will be permitted. Detour signage will remain in place.
Posted October 9, 2026: The Town of Midland and CM Drain will be conducting watermain work on Eighth Street that will cause a full road closure to the intersection at Hugel Avenue and Eighth Street from October 13 at 7am to October 14 at 6pm. The road will remain open to local traffic only, however no through-traffic will be permitted. Detour signage will be in place.
Posted July 28, 2026: The Town of Midland and CM Drain will be conducting watermain work on Eighth Street that will cause a temporary disruption to water service on July 31 from 9am–4:30pm. Temporary Water Shutoff Notices have been issued to impacted properties. If inclement weather is experienced, this work will be completed on August 4 from 9am–4:30pm.
Posted July 27, 2026: Construction on Eighth Street has begun. Eighth Street is fully closed (local traffic only) from Yonge to Hugel for the duration of the project. The notices of construction previously hand-delivered to nearby properties contain full information on property impacts, site safety, utility interruptions, curbside collection, and property access.
Posted July 8, 2026: Work is expected to begin the week of July 27. The contractor will be completing a precondition survey to record existing conditions of the adjacent buildings prior to construction. Notices of construction were hand-delivered to nearby properties. The notices include information on property impacts, site safety, utility interruptions, curbside collection, and property access.
Posted June 18, 2026: Construction activity is scheduled to begin in mid-August and be completed by the end of October. Nearby properties have received two notices so far, and will be receiving a construction notice a few weeks prior to work starting.
Posted April 23, 2026: The construction project is currently being advertised to interested bidders. Work is expected to be awarded to the successful contractor and work initiated by June 1, 2026, with an anticipated completed date by October 31, 2026, subject to change. A notice of upcoming construction is being hand-delivered to nearby properties.