Yonge Street Reconstruction Project

Project Status: Completed


Latest Update

Posted July 20, 2026

This project was deemed complete on June 18; however, due to some extended finishing works, a shift in traffic (3 lanes will be shifted to 2 lanes) is scheduled on Yonge Street from 7am on Tuesday, July 21, to 7pm on Wednesday, July 22. Expect delays and slower traffic through the area between Sixth Street and Fourth Street.

Yonge Street underwent reconstruction and resurfacing from Second Street to Norene Street, King Street to Second Street and Norene Street to County Road 93. The project started in May 2025 and was deemed complete in Spring 2026.

This project includes: 

  • New sanitary sewer replacement and associated services.
  • New watermain replacement and associated services. 
  • New barrier curb and gutter, restoration of all disturbed areas including driveways, topsoil, sod and surface elements.
  • New asphalt from King Street to County Road 93.
  • New cycling lanes.

Project Area

Yonge Street Reconstruction

Yonge Street Reconstruction Phases

Between Second St and Fourth St May 2025 to July 2025

Between Fourth St and Sixth St July 2025 to August 2025

Between Sixth St and Norene St August 2025 to November 2025

Between Norene St to County Road 93 May 2025 to August 2025

Between King St to Second St August 2025 to October 2025

Surface works on Yonge Street between Seventh street and Norene Street Spring 2026

Who to Contact

If you have any questions or comments about the Yonge Street Reconstruction project contact Trevor or Chris using the contact information below. Damages should be reported to the contract administrator or contractor as soon as possible.

Tatham Engineering

Trevor Stapleton
Contract Administrator
705-717-0550
tstapleton@tathameng.com

Maacon Construction

Zac Nicol
Public Relations Officer
519-372-5966
zac@maacon.com

 

Town of Midland

Bailee Yasher
Senior Project Manager
705-526-4275 x2207