Posted September 3, 2026
The Little Lake Park east washroom is closed effective immediately and will remain closed throughout the long weekend due to splash pad construction. The west and central washrooms will remain open and available for public use during this time. Thank you for your understanding and patience.
Posted August 26, 2026
Construction of the splash pad is taking longer than originally anticipated due to delays on site. As a result, the estimated completion date has moved from the end of August to mid-September.
Work continues on site, and the project team is working closely with the contractor to complete the remaining construction activities as efficiently as possible while ensuring all work meets required quality and safety standards.
We understand this revised timeline may be disappointing for residents and families who are looking forward to using the splash pad. We appreciate the community's patience and will continue to provide updates as key milestones are reached.
The project timeline below has been updated accordingly.
Posted August 5, 2026
The contractor is pouring more concrete this week for the splash pad and backfilling around the splash pad area.
Posted July 23, 2026
The east parking lot in Little Lake Park and the associated roadway leading to it will be closed Monday, July 27, through Thursday, July 30, due to construction activities for the splash pad. Please park in other parking lots within Little Lake Park and use the trail networks to access park amenities including the playground, dog park, community garden, and volleyball courts. Access to the boat launch will be closed due to the road closure.

Posted July 15, 2026
Construction of the pad has commenced, and plumbing will be starting this week.

Posted June 17, 2026
Construction will begin on June 22, 2026, with removals of sand/fill and prep work for concrete. There will be six volleyball courts out of service while the project is being completed, leaving three in service throughout the splash pad construction. The volleyball club has been notified accordingly. Once the splash pad project is complete in August, all six volleyball courts will have new nets and poles.